A project has the following cash flows. Normally cash flows are assumed to happen at the given time. But here, assume that the cash flows are received smoothly over the year. So the $250 at time 2 is actually earned smoothly from t=1 to t=2:
Project Cash Flows | |
Time (yrs) | Cash flow ($) |
0 | -400 |
1 | 200 |
2 | 250 |
What is the payback period of the project in years?