Fight Finance

Courses  Tags  Random  All  Recent  Scores

Question 190  pay back period

A project has the following cash flows:

Project Cash Flows
Time (yrs) Cash flow ($)
0 -400
1 0
2 500
 

What is the payback period of the project in years?

Normally cash flows are assumed to happen at the given time. But here, assume that the cash flows are received smoothly over the year. So the $500 at time 2 is actually earned smoothly from t=1 to t=2.